Halifax Details

Check Out Our Detailed Timeline for Halifax County

The tower schedule can change due to leasing issues or other factors. The status will be updated as changes occur.

*The map terms “Excellent, Good, Fair” refer to the chance of getting service signal in each zone. Service is not guaranteed for every address within the tower coverage area, each address must be checked individually.

Brookneal Water Tower – Tower #1134

Serves the areas around Brookneal,  North Rt 40 & Rt 501

Status Note: Lease is signed. Loading of the tower for service will begin immediately after lease signing.   

Date of Status: 9/1/2018

Estimated Completion Date: 9/25/2018

DMV RT 40 – Community Project #1631

Status Note:  This project is completed.

Date of Status: 9/1/2018

Estimated Completion Date: 8/25/2018

*This project is for the DMV.

Halifax Water Tower – Tower #1630

Serves the areas around Halifax, Hermosa & Nanural

Status Note: Lease for the tower is completed. Loading for tower can now begin, scheduled start in the week of 9/20. This tower will be used as a backhaul to the Internet to towers in the southern part of the county.

Date of Status: 9/1/2018

Estimated Completion Date: 10/1/2018

VOLE – Tower #1604

Serves the areas around Acorn, Republican Grove, RT 40, Nathalie

Status Note: Pre-Engineering approved, Lease negotiation has been completed and leasing negotiation is in process but taking longer than expected.

Date of Status: 9/1/2018

Estimated Completion Date: 10/15/2018

Nathalie Tower – Tower #1611

Serves the areas around Rt 501/Rt 603, Republican Grove, Acorn & Nathalie

Status Note: This tower’s owner is requiring a certification for loading which is new to SCS. SCS is pursuing the certification required as well as negotiating with a contractor for loading tower. This tower is still a priority due to the impact it will have on homes and several businesses. Leasing is in process in parallel to the tower loading certification. SCS has obtained a quote to load tower and will have a decision shortly.

Date of Status: 9/12/2018

Estimated Completion Date: 10/25/2018

Dan River – Tower #1609

Serves the areas around Rt 58 West

Status Note: This tower has been moved up in priority as it will be needed for a new tower in Virgilina. Lease negotiation has been completed and leasing process will start in September.

Date of Status: 9/1/2018

Estimated Completion Date: 11/15/2018

Crystal Tower – Tower #1607

Serves the areas around Alchie, Youngers Store, Nathalie, Hill Grove

Status Note: Pre-Engineering approved, Lease negotiation has been completed and leasing process will start in August.

Date of Status: 9/1/2018

Estimated Completion Date: 12/1/2018

Glad Tower – Tower #2301

Serves the areas around Hermosa,  Rt 40 & Brookneal

Status Note: Lease negotiation has been completed and leasing process will start 60 days before scheduled completion.

Date of Status: 9/1/2018

Estimated Completion Date: 1/1/2019

Plywood Tower – Tower #1605

Serves the areas around Plywood, Wolf Trap & South Boston

Status Note: Lease negotiation has been completed and leasing process will start 60 days before scheduled completion.

Date of Status: 9/1/2018

Estimated Completion Date: 2/1/2019

Virgilina – Tower #1661

Serves  Virgilina

Status Note: This will be a new small tower to be built by the county. The estimation date will be moved up according to when actual tower build will be completed.

Date of Status: 9/1/2018

Estimated Completion Date: 2/1/2019

Boston Tower – Tower #1603

Serves the areas around South Boston & Terry’s Corner

Status Note: Lease negotiation has been completed and leasing process will start 60 days before scheduled completion.

Date of Status: 9/1/2018

Estimated Completion Date: 3/1/2019

Cluster Tower – Tower #1602

Serves the areas around Cluster Springs & Woodlawn

Status Note: Lease negotiation has been completed and leasing process will start 60 days before scheduled completion.

Date of Status: 9/1/2018

Estimated Completion Date: 4/1/2019

Craw Tower – Tower #1608

Serves the areas around Turbeville

Status Note: Lease negotiation has been completed and leasing process will start 60 days before scheduled completion.

Date of Status: 9/1/2018

Estimated Completion Date: 5/1/2019

Clover Water Tower – Tower #1610

Serves the areas around Rt 58 West

Status Note: Lease negotiation has been completed and leasing process will start 60 days before scheduled completion.

Date of Status: 9/1/2018

Estimated Completion Date: 6/1/2019

High Tower – Tower #1606

Serves the areas around Rt 58 East

Status Note: Lease negotiation has been completed and leasing process will start 60 days before scheduled completion.

Date of Status: 9/1/2018

Estimated Completion Date: 7/1/2019