Pittsylvania Details

Check Out Our Detailed Timeline for Pittsylvania County

The tower schedule can change due to leasing issues or other factors. The status will be updated as changes occur.

*The map terms “Excellent, Good, Fair” refer to the chance of getting service signal in each zone.

White Oak Tower – Tower #1101

Serves areas near White Oak, Chatham, Dry Fork, Keeling, Mt. Hermon, Hopewell, Blairs, Lucks, & Ebenezer

Status Note: Upgraded to increase signal strength. This has been completed allowing more successful installations!

Date of Status: 6/1/2018

Estimated Completion Date: Completed


Airy Tower – Tower #1105

Serves the areas around Mt. Airy, Renan, Glenland, Hermosa, & Greenfield

Status Note: Tower loading was completed with only electrical service connection task to be completed.

Date of Status: 6/27/2018

Estimated Completion Date: 6/25/2018


Laurel Grove FD 

Serves the Laurel Grove Dire Department and nearby homes.

Status Note:  This is a recent addition to the County project. SCS is currently testing and prepping required steps to install services for the Fire Department. It may be possible to provide services to the local homes.

Date of Status: 6/27/2018

Estimated Completion Date: 7/15/2018


*This project is for the fire department.

Grit Tower – Tower #1106

Serves the areas around Wards/Grit Intersect, Monte Vista, & Hill Grove

Status Note: This tower’s priority has been changed due to service requests numbers. Loading will begin at end of June.

Date of Status: 6/27/2018

Estimated Completion Date: 7/25/2018


Callands Tower – Tower #1120

Serves the areas around Callands, Rondo, Banister, Flint Hill, Hollywood, Swanson Mill, Mt. Cross/Franklin Intersect

Status Note: Loading process will begin at end of June.

Date of Status: 6/27/2018

Estimated Completion Date: 7/30/2018


Brosville Tower – Tower #1110

Serves the areas around Brosville, Westfork, Soapstone, Berry Hill, Bachelors Hall

Status Note: Engineering

Date of Status: 6/15/2018

Estimated Completion Date: 8/1/2018


Kentuk Tower – Tower #1130

Serves the areas around Kentuk

Status Note: Engineering

Date of Status: 6/15/2018

Estimated Completion Date: 9/1/2018


Zion Tower – Tower #1134

Serves the areas around Zion

Status Note: Engineering

Date of Status: 6/15/2018

Estimated Completion Date: 11/1/2018


Rock Tower – Tower #1107

Serves the areas around Gretna & Motley

Status Note: Engineering

Date of Status: 6/15/2018

Estimated Completion Date: 12/1/2018


  

Hurt Water Tower – Tower #1135

Serves the areas around Hurt

Status Note: Not started

Date of Status: 6/15/2018

Estimated Completion Date: 1/1/2019


Gretna Water Tower – Tower #1137

Serves the areas around Gretna, Farmers, & Galveston

Status Note: Not started

Date of Status: 6/15/2018

Estimated Completion Date: 2/1/2019


Hargrave Water Tower – Tower #1133

Serves the areas around Chatham

Status Note: Not started

Date of Status: 6/15/2018

Estimated Completion Date: 3/1/2019


Tightsqueeze Water Tower – Tower #1132

Serves the areas around Tightsqueeze

Status Note: Not started

Date of Status: 6/15/2018

Estimated Completion Date: 4/1/2019


Brosville Water Tower – Tower #1138

Serves the areas around Brosville

Status Note: Not started

Date of Status: 6/15/2018

Estimated Completion Date: 6/1/2019